Process of general assembly line:
1. The crane discharge items at the entrance of warehouse→information enter (Establish internal code after weighing)
2. Rolling material enter warehouse
3. Ex-warehouse on schedule
4. Manual unpacking and appearance inspection of rolled products
5. Appearance inspection, disposal, code scanning records
6. Manufacture information enter
7. Annealing → Completion information entry → Blanking and turnover
8. Load on P&F conveyor →Pickling and phosphating line → Processing information entry → Three roll inspection (manual) → Acid pickling → Completion information entry → Blanking and turnover → Rail car to wire drawing machine → Processing information entry → Wire drawing (intermediate wire) → Completion information entry
9. Ground rail to annealing furnace → Processing information entry → Annealing → Completion information entry → Blanking and turnover
10. Load on PF line to pickling line → Processing information entry → Bulk roll inspection (manual) → Pickling → Completion information entry → Blanking and turnover → Rail car to wire drawing machine → Processing information entry → Wire drawing (finished wire) → Completion information entry